Construction & engineering debt recovery
Milestone payments, retention holdbacks, and variation disputes. We recover what contractors and subcontractors are owed.
Recovery rate
Recovered in 2024
Countries
Avg. resolution
Construction has a payment culture that would be considered genuinely alarming in any other industry. A subcontractor can complete six months of work, pass every inspection, receive formal sign-off on each milestone, and still wait another year for full payment. This isn't a bug in the system — it's a feature. The construction industry has, over several decades, developed an elaborate architecture of delayed payment that it has somehow convinced itself is normal. Retention clauses, pay-when-paid provisions, final account negotiations that drag on longer than the actual build — these aren't exceptions. They're standard operating procedure.
The numbers are extraordinary. A structural steelwork subcontractor completes £1.2 million of work on a commercial development. Five percent is held as retention: £60,000, locked away for 12 months pending the defects liability period. The period expires. The building is occupied. Tenants are paying rent. The main contractor's commercial team, asked to release the retention, suddenly discovers "ongoing snagging issues" that nobody mentioned during the previous 12 months of apparently satisfactory occupation. The retention remains unreleased.
THE CHALLENGE
Industry-specific pain points
Milestone & Progress Disputes
Work is completed but payment is withheld pending sign-off that never comes.
Retention Holdbacks
5-10% retentions stack up across multiple projects, locking significant capital for months or years.
Variation Claim Rejections
Change orders were verbally agreed but the client now disputes the additional charges.
The subcontractor, who financed the work, the materials, and the labour from their own cash flow, continues to wait. Variation claims are the construction industry's most popular payment avoidance mechanism. Here's how it works: a client requests additional work. The site manager agrees. The work is carried out. The cost is recorded. Then, when the invoice arrives, the client's quantity surveyor discovers that no formal variation order was issued. The work is complete, visible, and physically incorporated into the building, but the paperwork doesn't exist in precisely the format the contract requires.
International construction adds jurisdictional complexity to an already complicated payment landscape. A German subcontractor working on a Dutch project under an English-law FIDIC contract with a French main contractor — four jurisdictions, each with different construction payment legislation, retention rules, and adjudication procedures. Determining which law applies, which courts have jurisdiction, and what remedies are available requires expertise that most construction companies simply don't have in-house.
OUR APPROACH
How INTERCOL recovers construction debts
Contract & Variation Review
We analyse construction contracts, variation orders, completion certificates, and payment schedules.
Adjudication Awareness
Many jurisdictions have rapid adjudication procedures for construction disputes — we use them.
Lien & Bond Mechanisms
Where applicable, we pursue mechanic's liens, performance bonds, and retention release claims.
Subcontractor Chain Recovery
We trace payment obligations through the contractor chain to the party ultimately responsible.
The good news — and there is good news — is that many jurisdictions have recognised the construction industry's payment problem and legislated solutions. The UK's Construction Act introduced statutory adjudication: a binding decision within 28 days. Germany's BGB §650 provides specific payment protections for construction work. Several EU countries have implemented late payment directives with teeth. These instruments exist precisely because legislators looked at construction payment practices and concluded that the industry was incapable of regulating itself.
INTERCOL's construction recovery leverages these statutory protections alongside commercial pressure. We understand JCT, FIDIC, NEC, and local-form contracts. We know the difference between a genuine defect claim and a retention release stalling tactic. And we know that a well-constructed demand — one that references the correct contract clause, cites the applicable legislation, and makes clear the consequences of continued non-payment — resolves more construction disputes than a year of "chasing" phone calls from your accounts team.
SEE HOW IT WORKS
Construction is the single most affected industry by late payments in the EU. The sector accounts for approximately 20% of all insolvencies globally — 17% in Germany, 18% in the UK, 22% in France.
In England and Wales alone, 3,931 construction firms became insolvent in 2025, representing a larger share than any other sector.
The European Commission identifies construction as the sector where late payments are most likely to cause bankruptcy.
Source: UK Insolvency Service (GOV.UK), January 2026 · Allianz Trade Global Insolvency Outlook, 2025 · European Commission
REAL-WORLD CASES
Scenarios we handle every day
Retention Release Stalling
A German subcontractor completes structural steelwork on a €1.2M project for a Dutch main contractor. The 5% retention of €60,000 is held for 12 months pending defects liability. The period expires. The main contractor refuses to release it, citing 'ongoing snagging' that doesn't exist.
Typical resolution: 58 days
Variation Order Payment Refusal
A UK mechanical contractor installs €23,000 of additional HVAC work on a Spanish hotel project. The variation was verbally agreed by the site manager and confirmed in an email chain. The client's commercial team now refuses payment, claiming no formal variation order was issued.
Typical resolution: 42 days
Main Contractor Insolvency Shield
An Italian flooring specialist completes €34,000 of work. The main contractor enters 'concordato preventivo' (Italian restructuring). The specialist is told to join the creditor queue. Meanwhile, the building owner continues the project with a new contractor.
Typical resolution: 67 days
Why choose INTERCOL for construction recovery
Contract & Variation Expertise
Construction contracts are complex. We analyse JCT, FIDIC, NEC, and local-form contracts to identify your exact payment entitlements.
Adjudication & Payment Act
In jurisdictions with construction-specific legislation (UK Housing Grants Act, German BGB §650), we use rapid adjudication and statutory payment mechanisms.
Retention & Bond Recovery
We pursue retention releases, performance bond claims, and parent company guarantees when available.
Subcontractor Protection
We understand the power imbalance between main contractors and subcontractors and use legal mechanisms designed to protect payment rights down the chain.
COVERAGE
Where we recover construction debts
Operating across 40+ jurisdictions. Don't see your debtor's country? Contact us — we likely have a solution.
COMMON QUESTIONS
Yes. Retention recovery is one of our most common construction cases. Once the defects liability period expires, retention must be released. We pursue release formally, and if the main contractor stalls, we escalate through the appropriate legal mechanism. We also challenge illegitimate defect claims used to justify continued retention.
In many EU jurisdictions, 'pay when paid' clauses are unenforceable or severely restricted. The UK Construction Act, for example, renders most such clauses void. We analyse your contract and local legislation to determine whether this defence holds — in most cases, it doesn't.
Yes. In jurisdictions that offer statutory adjudication (UK, Australia, Singapore, and increasingly in EU countries), we coordinate rapid adjudication proceedings. Adjudication produces a binding interim decision, typically within 28 days — far faster than litigation.
Final account disputes are common in construction. We separate the agreed elements (undisputed sums) from the disputed items, and pursue immediate payment of the undisputed portion. For the disputed balance, we help you build the case for negotiation or adjudication.
If the main contractor is insolvent, direct recovery may be limited. However, we explore alternative routes: direct claims against the building owner (in jurisdictions where this is available), bonds and guarantees, retention of title over unfixed materials, and parent company liability. Insolvency doesn't always mean zero recovery.
✈️ TURBULENCE REPORT™ — Construction Sector
Real quotes. Real contradictions. All sourced from official filings.
— Carillion Annual Report 2015
£7 billion in debt. £29 million in cash. Compulsory liquidation January 2018. CEO fined £237,700 by FCA (Feb 2026) for "misleading statements." 30,000 suppliers got nothing. Seven years later, 60 of 84 companies still can't pay creditors a penny.
Source: FCA Final Notice Feb 2026 · PwC Administration Reports · Insolvency Service
Screen your customers →— Chairman Hui Ka Yan, employee letter, January 2023
$300 billion default — the largest in corporate history. Chairman detained by police (Sep 2023). Auditor PwC quit. 1.6 million homebuyers left with deposits on unbuilt homes. Triggered an entire sector crisis. Hong Kong court ordered liquidation (Jan 2024).
Source: SCMP Jan 2023 · Hong Kong Court Filing Jan 2024 · Evergrande Stock Exchange Filings
Screen your customers →Your construction debtor doesn't need to be Carillion-sized to leave you with nothing. The warning signs are the same at every scale. Brief us on the case →
Check in your construction case
Free assessment. No obligation. A specialist reviews your case within 24 hours.